Here is a summary of the project history outlining the key events in the development of the Holyrood Building.
1997
| Month |
Milestone |
| July |
White Paper 'Scotland's Parliament' published |
| December |
Choosing a Site: Short-listed sites published
Holyrood added to short-list
|
| December |
Exhibition of short-listed sites in Edinburgh and Glasgow
|
1998
1999 – Before Construction and Design Phase G
| Month |
Milestone |
| January |
Large scale archaeological excavations commence |
| April |
Preconstrucion work begins on site
Designs on Display: Public exhibition of final scheme designs
|
| May |
Launch of Hoardings Artwork initiative (Future Face of Your Parliament) |
1999 – Construction and Design Phase begins
| Month |
Milestone |
| June |
Responsibility for the project transferred from Secretary of State to the Scottish Parliamentary Corporate Body
1st Parliamentary debate on the project
Demolition works completed
|
| July |
Main construction work began on site
|
| September |
Revised chamber design agreed |
| October |
First pour of concrete for substructure of MSP building including car park
Children's artwork unveiled on site hoardings
|
| November |
First Tower crane arrived on site
|
2000
| Month |
Milestone |
| March |
Spencely Report published
|
| April |
Construction of MSP building frame started
2nd Parliamentary debate on the project
|
| June |
1st vaulted ceiling of MSP building installed on site
Holyrood Progress Group established
|
| July |
Death of Enric Miralles
|
| September |
Auditor General reports on Holyrood |
| October |
New Parliament Building Visitor Centre opened
Death of Donald Dewar, First Minister
|
| December |
Contract for Kemnay Granite awarded |
2001
2002
| Month |
Milestone |
| September |
First beams for Debating Chamber roof installed
|
| October |
First of the MSP feature windows installed
|
| November |
New Parliament Building Visitor Centre closed |
| December |
Building Information Centre opened at The Tun |
2003
| Month |
Milestone |
| March |
Construction began of vaulted roofs in the committee rooms.
Completion of beams and steelwork for chamber roof. Steelwork in the lobby roof in place.
|
| June |
Lord Fraser of Carmyllie, former Lord Advocate, appointed to lead investigation into cost of the new Parliament building
|
| July |
SPCB started monthly progress reports for Finance Committee
|
| December |
Chamber crash deck removed
MSP Offices completed
Queensberry House building work completed
|
2004
| Month |
Milestone |
| January |
North elevation of Canongate Wall is completed
Debating Chamber ceiling presented to Media
|
| March |
Last tower crane leaves Holyrood site |
| May |
Installation of desks and carpet in the Debating Chamber begins
|
| August |
Staff move in to Holyrood Building |
| September |
Holyrood Inquiry Report published
Scottish Parliament met for first time in Holyrood
|
| October |
Official opening of the Building
Guided tours began
|
| November |
Holyrood reached 100,000 visitors |